| Construction Start |
Client |
Description |
Location |
| Oct-08 |
TransCanada PipeLines |
55 kms of 36" pipeline incl. 543m HDD river xg. |
Wabasca, Alberta |
| Jan-08 |
Suncor Energy |
Tailings and Slurry Line Maintenance plus misc Civil Projects |
Fort McMurray, Alberta |
| Nov-07 |
Suncor Energy |
Tailings and Slurry Line Maintenance plus misc Civil Projects |
Fort McMurray, Alberta |
| Jan-07 |
Inter Pipeline Fund |
102 kms of 42" Pipeline |
Fort McMurray, Alberta |
| Jan-07 |
CNRL |
20" Gas Line including One Major Haul Road Xing |
Fort McMurray, Alberta |
| Sep-06 |
CNRL |
6 -18" Water Lines including Major Excavation |
Fort McMurray, Alberta |
| Jan-06 |
Suncor Energy |
Tailings and Slurry Line Maintenance plus misc Civil Projects |
Fort McMurray, Alberta |
| Jan-06 |
Pembina |
Algar to Cheecham Pipeline Project - Install approximately 56 kilometers of NPS 16 |
Fort McMurray, Alberta |
| Jan-06 |
Suncor Energy |
Tailings and Slurry Line Maintenance plus misc Civil Projects |
Fort McMurray, Alberta |
| Jan-03 |
Alberta Oil Sands Pipeline LTD. |
Stage 3 Looping Project, Green Zone Pipeline Construction 73 km of 24" and 44 km of 30" |
Fort McMurray, Alberta |
| Nov-02 |
Encana Empress Deepcut Project |
672 meters of 30" Including support of 300 meter HDD |
Empress, Alberta |
| Oct-02 |
TransCanada PipeLines |
Hydrostatic Retest Program Alberta, 2000 |
Sundre, Edson Valleyview, Alberta |
| Sep-00 |
Alliance Pipeline Limited Partnership |
Contract B - Spread 9SB 94.8 km 36" |
Weyburn, Sask. |
| May-00 |
Alliance Pipeline Limited Partnership |
Contract B - Spread 4W 53.1 km 42"; 59.5 km 36" Including support of 1,100 meter HDD of Athabasca River |
Whitecourt, Alberta |
| Jan-00 |
Alliance Pipeline Limited Partnership |
Contract B - Spread 9SA 139.2 km 36" |
Estevan, Sask. |
| Sep-99 |
Alliance Pipeline Limited Partnership |
Contract B - Spread 5S 216.4 km 36" |
Central Alberta |
| May-99 |
TransCanada PipeLines |
Spread 99A - 41.4 km 42" |
Kenora & Nipigon, Ontario |
| Nov-98 |
TransCanada PipeLines |
Spread 98D - 71 km 42" |
Dryden & Thunder Bay, Ontario |
| May-98 |
TransCanada PipeLines |
Spread 98A-PMP & Hydrostatic ReTesting MLV 51 and MLV 106A; 30"/36" Pig Launchers |
NW Ontario |
| Dec-97 |
NOVA Gas Transmission |
NPS 42 Western Alberta System M/L Loop, N. Creek Section, 20 km 42"; NPS 48 Central Alberta System M/L Loop-Gayford, Lone Pine, Harmattan Sections; 80 km 48" (RMS Welding Systems) |
Pincher Creek and Airdrie, Alberta |
| Jun-97 |
TransCanada PipeLines |
Spread 97C, 51 km 42" and Hydrostatic ReTesting |
Geraldton, Longlac, Ontario |
| Dec-96 |
Colt Engineering |
Express Pipeline, SE Alberta 235 km 24" oil |
Red Deer River to Wild Horse, AB |
| Aug-96 |
TransCanada PipeLines |
Spread 96A, 24.7 km 42" and 48" Lake Wahtopanah Crossing |
Spruce Siding, Falcon Lake, Man. |
| Dec-95 |
TransCanada PipeLines |
Spread 96B, 57 km 42" and Hydrostatic Retesting |
Eaglehead, Potter Geraldton, Ontario |
| Jun-95 |
Union Gas |
Trafalgar Line Replacements |
Cambridge, Ontario |
| May-95 |
TransCanada PipeLines |
Various Pipeline Projects in Ont. Spread 95C, 22 km 42" |
North Bay, Ontario |
| May-95 |
TransCanada PipeLines |
Pipeline Maintenance Program Spread 95A, MLV 55-105, 6 km Replacement |
Northern Ontario |
| Nov-94 |
NOVA Gas Transmission |
NPS 48 Eastern Alberta System Mainline Loop #3 (Makepeace & Matzhiwin East Sections) 54 km 48" |
Southern Alberta |
| Jul-94 |
NOVA Corporation |
Edson Mainline Looping/Grande Prairie Lateral; 98 km 42 & 48" McLeod River Crossing |
Edson, Alberta |
| Nov-93 |
TransCanada PipeLines |
Various Mainline Construction Projects in S. Ontario, Spread Y; Welland River, Lyons Creek QEW crossings, 17.4 km 36"; 19.8 km 24" |
Niagara Falls, Cornwall and Bracebridge, Ontario |
| May-93 |
TransCanada PipeLines |
Various Mainline Construction Projects in Manitoba & Ontario Spread T1, 55.8 km 42" |
Falcon Lake, Manitoba Upsala and Ignace, Ontario |
| Nov-92 |
TransCanada PipeLines |
Winter Mainline Construction Projects in NE Ontario, Spread T4 53 km 42" |
North Bay, Ontario |
| Nov-92 |
Nova Corporation |
Bear Canyon Lateral NPS 30 Peace River Crossing 3.4 km 30" river crossing |
Northern Alberta |
| Jul-92 |
Westcoast Energy Inc. |
1992 Mainline Looping 34 km 30" & 36" loops |
Central & Southern B.C. |
| Jul-92 |
TransCanada PipeLines |
Various Mainline Construction Projects in Manitoba and Ontario Spread J. 40 km |
Hadashville, Man. to Kenora, Ontario |
| Nov-91 |
TransCanada PipeLines |
Various Mainline Construction Projects in NE Ontario, Spread G 145 km (90 miles) |
Kirkland Lake to North Bay, Ontario |
| Jun-91 |
TransCanada PipeLines |
Winter Mainline Construction Project in Manitoba and Ontario, Spread A, 99.2 km |
Kenora to Thunder Bay Ontario |
| Nov-90 |
Nova Corporation |
NPS 42 Edson Mainline Lateral Loop #2; NPS 42 Western Alberta System Mainline Loop and NPS 42 Empress East Crossover, 105 km |
Rocky Mountain House and Sundre, Alberta |
| Jun-90 |
Nova Corporation |
NPS 30 North Lateral Extension Loop No. 2, 85 km 30" |
Hanna, Alberta |
| Dec-89 |
Nova Corporation |
NPS 24 Huallen Lateral and NPS 20 Huallen Lateral Extension 29 km. 24"/16 km 20" |
Grande Prairie, Alberta |
| Dec-89 |
TransCanada PipeLines |
Line 100-3 Loop Spread 3C 63.2 km 42" |
Northern Ontario |
| Dec-88 |
Ocelot Industries |
988 Lone Pine Construction Bigstick Area, 9.5 km 14" |
Maple Creek, Saskatchewan |
| Nov-88 |
TransCanada PipeLines |
Line 500-2 Dawn Loop 9 km 36" gas line |
Sarnia, Ontario |
| Sep-88 |
TransCanada PipeLines |
1988 Pipe Maintenance Program Spread A and Spread B |
Northern and Southern Ontario |
| May-88 |
Nova Corp. of Alberta |
NPS 16 Liege Lateral Loop (North Section) 103.4 km 16" gas line NPS 6 MacKay River Lateral Loop-16.6 km 6" gas line |
Fort McMurray, Alberta |